SID WATKINS BUILDING

Key facts & challenges

Summary
The Walton Centre NHS Trust embarked on a major expansion programme to deliver a new three-storey building: Sid Watkins Building.
Sector
Healthcare
Project Value
£22m
Client
The Walton Centre NHS Foundation Trust
Contractor
Interserve
Subcontractor
Interserve
Location
Liverpool
Country
UK
Installation Description
"Hospitals have high quality - often heavy - fixtures but as the use of a room changes you're often limited to certain areas on the wall to install them. LaDura is strong enough to negate the need to go back and reinforce with plywood - meaning you can easily change the use and fittings of a room."
Installation
Identifying specialised best-in-class solutions was key to the success of this bid. Having worked closely with our technical team on two previous healthcare builds - Leighton Hospital, Crewe and The Christie Hospital, Manchester - Interserve were able to demonstrate key examples of product innovation and installation efficiencies. By using Siniat [LaDura] the need for using plywood pattresses was removed from the partitions, which in turn sped up the time taken to install, delivering the build 6 weeks ahead of schedule. "Siniat's technical team were on hand throughout the scheme to support our detailed production information process." Tom Gilbert-Rule – Gilling Dod Architects
Quote from
Kabir Salihi, Project Manager Interserve
Impact
"The project surpassed cost, time and quality objectives. Many of the staff have stated that since moving into the Sid Watkins Building in January 2015 it has had a really positive impact on the team. The whole environment, from lighting, technology to amount of space ensures it is conducive to working and a great environment to work in”.
Quote from
Paula Bamber, Head of Facilities and Developments

Project description

The Walton Centre NHS Trust embarked on a major expansion programme to deliver a new three-storey building: Sid Watkins Building. The new building houses an expanded 30 bed specialised rehabilitation centre, outpatient department, UK-leading pain management programme, education and training department, corporate offices and relatives overnight stay accommodation. The design brief was to focus on making the patient feel like they have entered a luxury hotel rather than a hospital, but as a healthcare facility the partitions need to meet extraordinary acoustic, fire, impact and hygiene demands.

Innovative, Smart & Efficient Solutions

Tested & Certified Solutions

Global Service Network